Curb and Gutter Replacement

Curb and Gutter Project

Project Location(s):

MacArthur Drive, Elm to Halsey
Eisenhower Road, Karban to MacArthur

Project Status:

Bid Award

Bid Opening Date:

Juy 19, 2023

Mandatory Pre Bid Meeting:

TBD

QuestCDN Number:

8572463

Construction Start Date:

Fall 2023

Construction Completion Date:

Fall 2023

Contractor:

TBD

Construction Engineer:

Christopher B. Burke Engineering, Ltd.

Design Engineer:

Christopher B. Burke Engineering, Ltd.

Awarded Contract Amount:

TBD

Adjusted Final Contract Amount:

TBD

Funding Source(s):

MFT and Local

 

Updates:

10/26/23

The contractor, Davis Construction, is planning to get started today or tomorrow on saw-cutting the limits of the 2023 Curb and Gutter Project. Next week, the removals will take place, followed by the installation of the new curbing. The project should be 100% complete (including restoration) by Thanksgiving.  The project is taking place along MacArthur Drive and Eisenhower Drive.  Proper traffic control will be put in place, and there will be no lane closures.